Excavation & Dirt Removal Calculator

Work out how much soil comes out of a hole, trench, pond or foundation dig. The calculator adds soil swell for your soil type and tells you how many truck or skip loads you need to haul it away.

Formula checked 23 Oct 2026 Free · no sign-up
Was this calculator helpful?

Found a bug or have a suggestion?

Leave it here and we will fix it and reply to you.

Embed this calculator on your website (free)

Copy this code into your page. It stays free and updates automatically.

How to use the excavation calculator

  1. Choose a rectangle or trench, or a round hole, and enter the size and depth.
  2. Enter how many identical holes (for example, 10 pier holes).
  3. Pick your soil type so the calculator can add swell.
  4. Enter your truck or skip size to see the number of loads, and a price per load for the hauling cost.

Excavation formulas

Bank volume = Length × Width × Depth (or π × r² × Depth) Loose volume = Bank volume × (1 + Swell %) Cubic yards = Cubic feet ÷ 27 Truck loads = Loose volume ÷ Truck capacity → round up

Worked example

Digging out a 20 × 10 ft area 3 ft deep in ordinary soil, hauled with a 10 yd³ truck:

  • Bank volume = 20 × 10 × 3 = 600 ft³ = 22.2 yd³
  • Loose volume = 22.2 × 1.25 = 27.8 yd³
  • Truck loads = 27.8 ÷ 10 = 2.8 → 3 loads

Typical swell factors

MaterialTypical swell1 yd³ in the ground becomes
Sand / gravel10–15%1.10–1.15 yd³
Common earth20–30%1.20–1.30 yd³
Topsoil / loam25–35%1.25–1.35 yd³
Clay30–40%1.30–1.40 yd³
Broken rock50–70%1.50–1.70 yd³

The calculator uses the middle of each range. If your contractor quotes a different figure, choose “Custom” and enter it.

Common excavation jobs

  • House or garage foundation: measure the outside of the footing plus working space on every side, and the depth from existing ground to the bottom of the footing.
  • Pool: for an in-ground pool, add about 1 ft (300 mm) around the shell for the walls and backfill, and use the average depth plus the base thickness.
  • Pier and post holes: use the round option with the number of holes.
  • Utility trench: length × bucket width × depth. A 100 ft trench, 1 ft wide and 2 ft deep, is 200 ft³ — about 7.4 yd³ in the ground or 9.3 yd³ loose.
  • Pond: for a bowl shape, use the full length and width with roughly half the maximum depth as a quick estimate.

Planning tips

  • Call before you dig. In the US, call 811 a few days ahead to have underground utilities marked; other countries have similar services.
  • Dig a little extra around foundations and footings for formwork and working space — often 1–2 ft (300–600 mm) each side.
  • Slope or shore trench walls deeper than 5 ft (1.5 m); trench collapses are a leading cause of construction deaths.
  • Keep good topsoil separate so you can reuse it for lawns and beds instead of paying to haul it away.
  • Check disposal rules — some sites charge by weight, and contaminated soil needs special handling.

Frequently asked questions

How do I calculate cubic yards of dirt to dig out?

Multiply length × width × depth in feet to get cubic feet, then divide by 27. A hole 20 × 10 ft and 3 ft deep is 600 ft³ = 22.2 cubic yards in the ground.

What is soil swell?

Soil expands when you dig it because the packed particles loosen and trap air. Common earth typically swells about 25%, so 22.2 yd³ in the ground becomes about 27.8 yd³ in a truck. Clay and broken rock swell more; sand and gravel less.

How many truck loads will I need?

Divide the loose (swelled) volume by your truck capacity and round up. 27.8 yd³ in a 10 yd³ dump truck is 3 loads.

What are typical swell factors?

As rough guides: sand and gravel 10–15%, common earth 20–30%, topsoil 25–35%, clay 30–40%, and blasted or broken rock 50–70%. Moisture and how tightly packed the ground was make a difference.

Will the dirt fit back in the hole?

If you backfill and compact it properly, soil usually fits back into the same space or slightly less (shrinkage). That is why leftover dirt is common after foundations and pipes — the structure takes up space too.

How much does a cubic yard of dirt weigh?

Usually about 2,000–2,700 lb (1–1.35 US tons) per cubic yard depending on moisture and soil type. Check truck weight limits as well as volume — a full load of wet clay may exceed the weight limit before the bed is full.

How we checked this calculator

We test this tool against worked examples before every release (last check: 23 Oct 2026, version 1.0.0). Results are estimates for planning — confirm critical figures with your supplier or a qualified professional.

References:

  • Peurifoy et al. – Construction Planning, Equipment and Methods: soil swell and load factors
  • Caterpillar Performance Handbook – typical material swell percentages